Projects Under Execution - KSA
| Project | Central Cooling Plant |
| Scope | MEP |
| Work Description |
Central Cooling Plant, Rafal - Riyadh, KSA
Chiller Cooling and Heating Plant
Engineering Procurement and Construction (EPC) contract to design, build, construct and warrantee
Cooling Load: 5 absorbent chillers 6,615 total TR capacity for cooling and heating use in the Rafal Tower and future potential projects
|
| Value AED | SAR 29,000,000.00 |
| Client | NTCC - National TriGeneration CHP Company |
| Consultant | |
| Main Contractor | |
| Period | May-12 to Mar-13 |