Executed Project - UAE
| Project | Staff & Labor Accommodation |
| Scope | MEP |
| Work Description |
G+3 Labor Camp - Dubai Investment Park, Dubai - UAE Built Up Area: 22,500 m2
G+3 Labour Accomodation + Sewage Treatment Plant + Service Yard
Engineering, Procurement, Installation & Commissioning of Complete MEP Works including Central Air Conditioning and Ventilation Systems, Plumbing and Drainage Systems, Fire Fighting System, Electrical Low Voltage and Low Current Systems
Cooling Load: District Cooling of 1125 TR total Cooling Load Connected Load: 4 Nos. MV Transformers of 1500 KVA each |
| Value AED | AED 5,700,000.00 |
| Client | Dubai Contracting Co. |
| Consultant | |
| Main Contractor | |
| Period | Aug-05 to May-06 |