Project | Greenfield Factory |
Scope | MEP |
Work Description |
Pepsicola Factory, Dubai Investment Park, No. 2, Dubai - U.A.E. Built Up Area: 66,000 m2
G+M+Roof, PB Filling Lines, PB Finished Goods WH, PB Raw Material WH, PB Utilities, PB Process, Administration Building, Sales & Warehouse Office Building, Entrance Building, WWTP, Employee Entrance, Sky Bridge, Transformer Zone 1, Transformer Zone 2, Transformer Zone 3, Employee Facility Building.
Engineering, Procurement, Installation & Commissioning of Complete MEP Works including Chillers, Central Air Conditioning and Ventilation System, Plumbing and Drainage Systems, Fire Fighting System, Electrical Low Voltage Systems, Solar & Hot Water System and all Mechanical/Industrial Piping Sytem.
Cooling Load: 9 Air Cooled Water Chillers of 3089TR total Cooling Load Connected Load: 16 Nos. MV Transformers of 1500KVA each
|
Value AED | AED 45,750,000.00 |
Client | Dubai Refreshment Company (DRC) |
Consultant | |
Main Contractor | |
Period | Dec-11 to Sept-12 |
Projects Under Execution - UAE